SCHEDULE FOR 2007-2008 FISCAL YEAR (APPROXIMATE DATES)
| 09/28/07 | Announcement inviting SERMCI proposals. |
| 11/02/07 | Deadline for submittal of proposals to the EHS Department. The EHS Dept. prepares a summary list of proposals received, along with recommendations for funding, and distributes them to the University Safety Committee for review. |
| 11/16/07 | EHS recommendations for funding SERMCI proposals are posted on this website. |
| 11/23/07 | Deadline for submission of appeals (additional written material or scheduling of a five minute presentation to the University Safety Committee at the 11/28/07 meeting. |
| 11/28/07 | The University Safety Committee reviews EHS recommendations, examines any supplementary information, and hears scheduled presentations. The Committee forwards a list of proposals recommended for funding to the Executive Vice President for Academic Affairs. |
| 12/19/07 | The Executive Vice President for Academic Affairs makes the final decision concerning the funding of projects. The EHS Director informs proposal sponsors of the Vice President’s decision. |
| 01/02/08 | The EHS Director begins processing approved projects. |
| 05/15/08 | Deadline to implement approved projects unless prior arrangements have been made with the EHS Director for an extension. Projects not implemented by this date are subject to withdrawal of funding. |